AVS 65th International Symposium & Exhibition | |
Vacuum Technology Division | Tuesday Sessions |
Session VT-TuP |
Session: | Vacuum Technology Division - Poster Session |
Presenter: | Kyo Shibata, KEK, Japan |
Authors: | K. Shibata, KEK, Japan Y. Suetsugu, KEK, Japan T. Ishibashi, KEK, Japan M. Shirai, KEK, Japan S. Terui, KEK, Japan K. Kanazawa, KEK, Japan H. Hisamatsu, KEK, Japan |
Correspondent: | Click to Email |
The SuperKEKB, which is an upgrade of the KEKB B-factory, is a high-luminosity electron-positron collider. To satisfy the requirements of high beam quality for positron injection into the SuperKEKB, a new damping ring (DR) with a circumference of 135.5 m was constructed in an upgraded injector system. The positron beam extracted from the injector linac with an energy of 1.1 GeV is stored in the DR for more than 40 ms, where the beam emittance is damped. Subsequently, the low-emittance beam is extracted and sent back to the linac to be accelerated to 4 GeV and injected into the SuperKEKB. The maximum stored beam current is 70.8 mA.
The vacuum system of the DR is divided into five sections. Main sections are two arc sections with a length of ~110 m in total. Since there is synchrotron radiation irradiation in the arc sections (critical energy: 0.8-0.9 keV), the average pressure over the entire ring during the beam operation is determined mainly by the pressure of the arc sections. The material of the beam pipes is aluminum alloy. The required beam lifetime determined by the residual gas scattering is longer than 1000 sec and it is expected that the average pressure should be lower than 1x10-5 Pa. Non-evaporable getter (NEG) pumps are mainly used with auxiliary ion pumps.
The construction of the DR was completed by the end of January 2017. It took more than two weeks from the start of the evacuation process from atmospheric pressure to the end of the activation of NEG pumps because of the small conductance of the beam pipes. The commissioning of the DR commenced in February 2017. When the beam was accumulated for the first time, the pressure exceeded 1x10-5 Pa with a beam current of ~1.5 mA. However, the pressure decreased quickly below 1x10-5 Pa. Subsequently, the pressure decreased gradually while the beam current was increased. The maximum stored current reached 11 mA on February 23. The residual gas composition of the pressure with the stored beam was typical of that expected for a vacuum system pumped by NEG pumps. Vacuum scrubbing has progressed smoothly thus far, and a beam lifetime of longer than 1000 sec was obtained with a stored beam current of 8 mA, when the beam dose was 0.7 Ah. The pressure distribution in the beam pipes was calculated using the Molflow+, and it is estimated that the photon stimulated desorption rate for CO at that time was reduced to ~1x10-4 molec./photon.
After beam tuning of the DR, the beam injection into the SuperKEKB commenced on March 27. No problems have been identified for the vacuum system to date.